Model Concession Agreement for PPP in Indian Ports Revised

Jawaharlal Nehru Port's 4th Container Terminal - A PPP Project Photo courtesy JNPT

By Joseph R Fonseca

In order to make port projects more investor friendly and make investment climate in the major port sector more attractive, the Indian Government has approved the revised Model Concession Agreement (MCA) for Public Private Participation (PPP) projects in Major Ports. Salient features of the revised MCA are as follows :

Providing exit route to developers by way of divesting their equity upto 100 percent after completion of 2 years from the Commercial Operation Date(COD). This is now similar to the MCA provisions of Highway Sector.
Under provision of additional land to the Concessionaire, land rent has been reduced from 200 percent to 120 percent of the applicable scale of rates for the proposed additional land.
Concessionaire would pay Royalty on "per MT of cargo/TEU handled" basis which would be indexed to the variations in the WPI annually. This will replace the present procedure of charging royalty which is equal to the percentage of Gross revenue, quoted during bidding, calculated on the basis of upfront normative tariff ceiling prescribed by TAMP. This will help to resolve the long pending grievances of PPP operators that Revenue share is payable on ceiling tariff and price discounts are ignored. The problems associated with fixing storage charges by TAMP and collection of Revenue share on storage charges which has plagued many projects will also get eliminated.
Concessionaire would be free to deploy higher capacity equipment/facilities/technology and carry out value engineering for higher productivity and improved utilization and/or cost saving of Project assets.
"Actual Project Cost" would be replaced by "Total Project Cost".
The new definition of "Change in Law" will also include (i) imposition of standards and conditions arising out of TAMP guidelines/orders, Environmental Law &Labour Laws and (ii) increase and imposition of new taxes, duties, etc for compensating the Concessionaire. Since the viability of the project was affected, concessionaire will now be compensated for the increase and imposition of new taxes, duties etc. except in respect of imposition/increase of a direct tax, both by Central & State Government.
Provision for commencement of operations before Commercial Operation Date(COD). This will lead to better utilization of assets provided by the Port in many projects before the formal completion certificate.
Provision regarding refinancing is aimed at facilitating availability of low cost long term funds to Concessionaire so as to improve the financial viability of the projects.
Extending the provision of SAROD-PORTS for redressal of disputes to the existing Concessionaires also by introducing the Supplementary Agreement to be signed between the Concessionaire and the Concessioning Authority.
Introduction of Complaint Portal for the use of port users.
A Monitoring Arrangement has been introduced for keeping periodical status report of the project.

Mar 12, 2018

 

Government Update

Trump Rails Against Oil Prices, OPEC Pushes Back

© Igor Groshev / Adobe Stock

U.S. President Donald Trump accused OPEC on Friday of "artificially" boosting oil prices

EU Suspects Tax Fraud at China's New Gateway to Europe

© milangonda / Adobe Stock

European Union and Italian authorities are investigating suspected wide-scale tax fraud by Chinese

DP World Should Rethink Port Deals in Somalia - Foreign Minister

(File photo: DP World)

Somalia's foreign minister said on Friday that Dubai state-owned port operator DP World should

Legal

EU Suspects Tax Fraud at China's New Gateway to Europe

European Union and Italian authorities are investigating suspected wide-scale tax fraud by Chinese criminal gangs importing goods via Greece’s largest port of Piraeus

First COI Issued Under Subchapter M

Pictured left to right: USCG Chief Warrant Officer Joel Reid; Marine Towing of Tampa ISM & Safety Coordinator, Capt. Scott Moorhead; and USCG Chief Warrant Officer Sean Goodman (Photo: Marine Towing of Tampa)

The U.S. Coast Guard has issued its very first certificate of inspection (COI) under the

Oldendorff Halts Guyana Operation Due to Rusal Crisis

(File photo: Oldendorff)

German shipping group Oldendorff Carriers is stopping its business in Guyana, the company said on

Maritime Apps