Sangomar FPSO Construction Starts in China

Image: SOFEC, A MODEC Group company

OE Staff

The conversion of a VLCC into an FPSO bound for Woodside's Sangomar project in Senegal has recently kicked off in China, the Australian oil firm said in a recent report.

The 323 meters-long very large crude carrier (VLCC) Astipal in February arrived in China, where it will, in Woodside's words, undergo "a metamorphosis" into the floating production storage and offloading (FPSO) facility for the Sangomar field.

Japanese firm MODEC is responsible for the delivery of the FPSO for the Sangomar field, Senegal's first offshore oil development. The FPSO conversion will take around two years.

The FPSO has so far been referred to as simply the Sangomar FPSO, after the name of the field where it will be deployed. According to Woodside, the FPSO now has a name, FPSO Léopold Sédar Senghor. The vessel was named after Senegal's first president from 1960 to 1980.

The Sangomar field, containing both oil and gas, is located 100 km south of Dakar, Senegal's capital, and will be the country's first offshore oil development.

First oil production from the FPSO Léopold Sédar Senghor is targeted in 2023, with the Sangomar Field Development Phase 1 targeting approximately 230 million barrels of crude oil, at an initial peak rate of 100,000 Bbls /day. The FPSO will be moored in approximately 780 meters water depth.image Credit: Woodside

Apr 5, 2021

 

Shipbuilding

Shipbuilding: FSG Expands Management Team

Carsten Treuer is FSG's new Head of Operations. Photo courtesy FSG

Flensburger Schiffbau-Gesellschaft (FSG) is expanding its management team further: in April

GTT Wins Tank Design Order for LNG Carrier Trio

French engineering firm GTT said it received an order from South Korean shipyard Hyundai Heavy Industries (HHI) for the tank design of three new liquefied natural gas (LNG)

Shipbuilding: HII Celebrates 154 Apprentice School Grads

About 154 graduates of The Apprentice School at Newport News Shipbuilding were honored during graduation exercises on April 17, 2021. Due to COVID 19, the ceremony was held outdoors at the Hampton Roads Convention Center to ensure the safety of all graduates and guests, as well as event staff. Photo by Ashley Cowan/HII

Huntington Ingalls Industries (NYSE:HII) hosted commencement exercises on Saturday, April 17, 2021

FPSO

VIDEO: After Modest 2020, the Years 2021 and 2022 Could Be 'Pretty Good' for FPS Orders

An FPSO - Credit: Ranimiro/AdobeStock

There's one thing that's certain about the price of oil, it goes up and it goes down

Keppel in Talks with Petrobras to Build FPSO for Buzios Field

An FPSO offshore Brazil; Credit: Ranimiro/AdobeStock

Singapore's Keppel Corporation has confirmed it has been in talks with the Brazilian oil company

Petrobras Suspends MODEC from Bidding for FPSO Projects

FPSO Cidade do Rio de Janeiro MV14 - Credit: MODEC

Brazilian national oil and gas company Petrobras has suspended Japanese FPSO specialist MODEC from

Maritime Apps